Status Update - 2/7/19
February 7, 2019
Status Item | Current Status | Previous Status | Comment |
Schedule | yellow | red | |
Resources | green | green | |
Financials | yellow | yellow | Small variance of actual vs budgeted hours requirement review activities |
Quality | green | green | |
Project Issues | green | green | timeline adjusted for the 1 month delay on requirement sign-off |
Key Deliverables | % | Comments | Timeline |
Requirement Sign-off | 73% | In Progress | 12/14 |
Data Model/Mapping | 80% | In Progress | 1/12 |
Build | 51% | In Progress | 3/28 |
Training/UAT | 0% | Not Started | 4/1 |